ENGINEERING GUIDE

Immersed UF Retrofit Survey | Tank, Headers and Lifting Access

Survey an existing tank for immersed UF using verified dimensions, water levels, hydraulic interfaces, isolation and a workable cassette removal path.

Browse technical guides ↗
Immersed UF Retrofit Survey | Tank, Headers and Lifting Access
HOSON LGJ1 immersed UF catalog assembly. Final dimensions and lifting information are specific to the ordered configuration.

Survey the operating system as well as the tank

A useful immersed UF retrofit survey captures the tank geometry, operating levels, process duty, service connections and the complete route for removing a cassette. Measure these items against fixed datums and record the current condition of the plant. The resulting survey should let a designer identify where the proposed replacement fits, which interfaces need modification and how operators will maintain it.

Use this guide when preparing a replacement assessment for an existing membrane bay. HOSON LGJ1 and LGJ2C are distinct catalog families that can be reviewed against the survey. Their final arrangement requires an approved configuration drawing. The numerical example below is hypothetical and demonstrates a preliminary clearance calculation. Structural capacity, lifting design and safe working procedures require assessment by the responsible professionals using the actual installation.

Start with records and verify them on site

Collect the latest process drawing, tank general arrangement, installed module list and piping layout. Add control narratives, commissioning records and recent operating trends. Mark the revision and date of each document. Ask operations staff to identify changes that were made after the drawings were issued, including temporary bypasses and equipment that remains isolated.

Create a survey drawing that distinguishes measured features from information copied from records. Use a consistent reference point and provide enough dimensions for another person to reproduce the layout. Photograph each bay from several identified viewpoints. Include a scale or dimension reference where practical and label photographs with the drawing location.

Keep uncertainties visible. If a support cannot be measured safely during operation, state the assumption and the planned opportunity to verify it. The designer can then avoid releasing fabrication against a dimension that has only been estimated.

LGJ2C catalog assembly. Compare the exact proposed cassette drawing with measured bay constraints before selecting a retrofit configuration.
LGJ2C catalog assembly. Compare the exact proposed cassette drawing with measured bay constraints before selecting a retrofit configuration.

Measure the usable envelope and hidden obstructions

Record internal tank length and width at the positions where the new equipment will sit. Check whether walls taper, surfaces are uneven or repairs protrude into the envelope. Measure floor slope, sumps, internal steps, rails and support brackets. Record the elevations of inlet openings, overflow structures, drains and existing pipe penetrations.

Show features above the waterline as well. Covers, crossbeams, cable trays and nearby pipework can restrict assembly or lifting. Note the space needed to reach bolts and disconnect joints. A cassette can fit its intended operating position while leaving insufficient room to connect it or remove a fastener.

Review solids access and tank cleaning with the operator. Identify where material accumulates and how it is removed. The proposed layout should preserve the practical means of draining, inspecting and cleaning the bay through its expected service cycle.

Record water levels with a common elevation datum

Measure the normal, low and high operating levels and the actual locations of level sensors. Record overflow and drain elevations on the same datum as the module supports. Identify which values are control setpoints and which have been observed. Ask for trend records showing the fastest level change during normal cycle transitions.

For a suction-driven system, the membrane depth and filtrate-side pressure need a consistent definition when determining the pressure across the membrane. Show the pressure tap elevation and the proposed reference level. This helps the supplier define the controller calculation and evaluate operation at the lowest permitted tank level.

State what causes a low-level shutdown and how the system restarts. Include any delay needed for upstream filling. If multiple bays share a feed channel, review whether isolating one bay changes levels or flow distribution in the others.

Map every service connection at the cassette

Prepare a connection schedule for permeate, air, drain, cleaning supply and any backwash service used by the proposed design. Measure port position and orientation against the same drawing references as the supports. Record pipe material, joint type, isolation valves and available movement for disconnection. Include the accessible area needed to operate each valve.

Confirm how the permeate header is supported and how pipe loads are kept within the assembly's approved limits. Identify sections that can trap air, retain chemical solution or remain pressurized after isolation. Ask the vendor to review the proposed arrangement through production, cleaning and integrity-test modes.

Check where instruments sample or measure each train. A retrofit that combines several permeate outlets into one header can change fault identification. Preserve enough isolation and measurement points to determine which train needs investigation when performance changes.

Develop a removal path from bay to service area

Trace the cassette from its installed position to the location where it can be inspected and serviced. Include the first vertical lift, rotation where needed, passage through the cover and movement to a designated landing area. Record obstacles that affect each part of the route. Check whether a removed cassette blocks access to adjacent equipment or emergency routes.

Obtain the configuration-specific lifting mass and certified lifting points. Include rigging geometry and any retained liquid or attached equipment in the lifting assessment. Catalog dry and wet weights help identify the need for a review, while the approved lifting plan uses the actual assembly and condition.

Review the working surface, drainage and containment at the landing area. Operators need access to disconnect, inspect and preserve the unit without placing it on an unsuitable surface. Confirm that the proposed maintenance method can be repeated after the site is fully occupied.

LGJ1 catalog assembly. Service access includes lifting and a suitable landing area for the actual ordered cassette.
LGJ1 catalog assembly. Service access includes lifting and a suitable landing area for the actual ordered cassette.

Use clearance arithmetic to expose missing inputs

Consider a hypothetical cassette that needs 2.40 m of vertical travel before its lowest point clears the tank opening. Assume the preliminary rigging arrangement needs 0.80 m between the lifting point and hook, and the lifting designer requires an additional 0.25 m positioning allowance. The illustrative minimum hook travel envelope is 3.45 m above the installed lifting-point position.

Compare that envelope with the actual hook approach and the obstruction profile. A roof beam may govern one part of the movement even if the overall roof height appears adequate. If the path requires a tilted lift or a changed rigging arrangement, return it to the lifting designer rather than treating the simple vertical calculation as approval.

Keep the assumptions beside the drawing. The example's value lies in revealing which dimensions and equipment choices the project still needs to confirm before ordering a replacement.

Hypothetical clearance componentAllowance
Travel to clear opening2.40 m
Preliminary rigging envelope0.80 m
Positioning allowance0.25 m
Illustrative combined envelope3.45 m

Check structural support and loads

Ask the structural engineer to review existing supports, anchorage, corrosion, concrete condition and the load introduced by the proposed arrangement. Include operating, maintenance and lifting cases as applicable. Provide load locations rather than a single total mass. A frame that occupies the same footprint may distribute its load differently across the tank floor or brackets.

Keep material compatibility in the review. Compare the proposed frame, piping and fasteners with the chemical environment and cleaning procedure. Identify where dissimilar materials, coatings or existing deterioration need attention. Obtain an approved detail for any modified support or penetration.

Document what can be inspected while the plant runs and what requires an outage. If a critical anchor or support remains concealed, define a hold point before installation. This gives the construction team a clear decision when the tank is available for final inspection.

Plan isolation and the temporary operating state

Describe how the owner will isolate, drain and release the bay for work. Map the temporary route for incoming water and the capacity available from other trains. Use actual production trends to identify the demand that must be supported during the outage. Include reserve storage and any permitted reduction in production.

List common resources that the remaining trains still need, including pumps, air, chemicals, electrical supply and controls. A bay can be hydraulically separate while sharing a component that must also be shut down for the retrofit. Identify those dependencies early enough to change the work sequence.

Prepare a rollback or contingency plan for a dimensional mismatch discovered after removal. Record which parts should be available on site and which modifications can be completed within the outage. Set the final verification points before the owner commits to removing the existing equipment.

Issue survey questions in the order they affect design

Classify unresolved survey items by the decision they block. An uncertain tank width can prevent cassette selection. An unverified support load can prevent structural approval. A missing cable route may be resolved later without changing the membrane layout. Give each item an owner, due date and the next opportunity for measurement. This helps the project team use a short outage effectively.

Prepare an information-request register with the designer and operator. Attach the relevant photograph or marked drawing to each question. State the proposed assumption and what would change if the measured result differs. Ask vendors to identify their own critical dimensions instead of treating every unmeasured detail as equally urgent.

For a hypothetical retrofit, suppose the proposed cassette appears to fit the tank but the header connection sits behind an existing beam. The next useful action is to measure the connection and disconnection envelope at that location. Increasing the number of photographs of the general tank will not resolve the interface. A targeted measurement may support a revised adapter, a moved header or a different cassette orientation, subject to design review.

Before fabrication release, hold a joint drawing review around the critical items. Record which dimensions are confirmed and which remain hold points for the installation team. Include the operator who will isolate and service the bay. Their access requirements can reveal an otherwise overlooked maintenance constraint while the drawing is still easy to change.

Connect the survey to commissioning evidence

Give the supplier a package containing the measured bay drawing, connection schedule, lifting envelope, photographs and current process data. Request a marked proposal that identifies every assumed dimension and required modification. Ask for the operating levels, control changes, isolation boundaries and tests needed for the offered LGJ1 or LGJ2C configuration.

At installation, record deviations and update the drawing before the bay is returned to normal duty. Verify the actual permeate and air connections, instruments, valve feedback and removal access. Establish operating baselines at agreed water conditions and demonstrate the specified integrity and quality checks.

Close the survey with an as-installed package that operations can reuse. A future replacement should begin with confirmed dimensions, accessible interfaces and a maintenance route that has already been checked against the installed equipment.